List Your Equipment  /  Dealer Login

Trenchless Construction, ICON Finishes Wash. Project

Mon August 31, 2009 - West Edition
Construction Equipment Guide


Trenchless Construction Services, of Arlington, Wash., has successfully completed one of the first pilot tube projects in Washington State using ICON’s slide rail system and Bohrtec BM400LS pilot tube micro-tunneling machine.

Sedro-Wooley, a small logging town in Washington State has recently begun increasing its trenchless pipe installation program due its proven success. Trenchless pipe installation minimizes disruptions and costs, while proving to be an effective way to install pipe.

Trenchless Construction Services, a trenchless pipe installation and replacement construction company, was the general contractor for the $3.5 million dollar Sedro-Wooley SR9 Township trenchless sanitary sewer improvement project. Trenchless was responsible for installing 14 manholes and 3,400 lineal ft. (1,040 m) of 15 in. (380 cm) diameter and 24 in. (60 cm) diameter gravity sewer pipes at a .16 percent grade. Trenchless methods were required for this project because the pipe was to be placed under and adjacent to State Highway Route 20 and State Highway Route 9.

“These methods were used because of a lack of detour options to maintain traffic flow,” said John Gustafson, owner/manager of Trenchless Construction Services. “The soil conditions, as well as the accuracy of pilot tube micro-tunneling, also made it the preferred method for the 15 inch and 24 inch portions of the project.”

Pilot tube micro-tunneling, also referred to as guided auger boring, was introduced in the 1990s for the installation of small diameter sewer pipes and water lines. Guided auger boring systems are similar to micro-tunneling systems with the addition of a guidance system. This accurate guidance system consists of a camera-mounted theodolite to ensure a high accuracy of the line and grade.

“We choose the Bohrtec guided auger machine because we knew it would give us bullet like accuracy,” said Gustafson.

Prior to construction, Trenchless sponsored a meeting with engineers, sub-contractors and Trenchless employees in order to get everyone on the same page. ICON, the New Jersey-based slide rail system manufacturer and Bohrtec pilot tube distributor and Mission Clay, the No Dig clay pipe manufacturer made presentations of their products.

“Our goal was to make sure all parties had a clear view of the project scope as well as the products we were going to use,” said Gustafson. “This was very beneficial as everyone was able to ask questions and get direct answers from the manufacturers.”

This project would require a total of six jacking pits in which Trenchless would place the pilot tube boring machine to jack the sewer pipe between manholes. These jacking pits were dug using a hydraulic excavator weighing 54,000 lbs. (24,500 kg).

Trenchless used ICON’s slide rail system to shore the six jacking pits, which were 11 ft. (3.3 m) wide by 20 ft. (6 m) long by 14 ft. (4.2 m) deep. This slide rail system is designed and built to withstand the jacking forces of the Bohrtec BM 400LS pilot tube machine.

“ICON’s slide rail system is very easy to install, which saved us a tremendous amount of time,” said Gustafson. “The slide rail system reduces setup time and is substantial enough to withstand the forces of the BM 400LS.”

This slide rail system also features temporary sheeting, which allows the contractor to extract small sheeting panels rather than large shoring panels to create an opening for the pipe installation.

The Bohrtec BM 400LS, with a jacking force of 150 tons (136 t) and 75 tons (68 t) of pull back force, can perform guided drillings in one, two or three phase procedures such as pilot drilling, reamer drilling with steel protective piping; alternative reamer drilling with pushing of product pipes at the same time and drilling with welded steel pipes.

Trenchless first performed the three-phase guided drilling installation with the 24 in. diameter clay pipe. The three-phase procedure consists of installing the pilot tube to secure an accurate line and grade. When the pilot tube reaches the receiving shaft, a 16 in. (40 cm) casing with an auger inside is connected to the last section of pilot tube in the jacking pit. The 16 in. casing with auger is jacked into place as the soil is extracted, following the pilot tubes. Once the casings and augers reach the receiving pit, a reamer is attached to the 16 in. casings. This reamer enlarges the bore hole to that required for the 24 in. clay pipe. The 24 in. clay pipe is then jacked to the receiving pit, following the 16 in. casings and reamer.

Trenchless then moved on to the next phase of the project, which was installing the 15 in. diameter pipe. Trenchless would only use the two- phase procedure for this installation.

“We were able to jack the clay pipe after the initial pilot tube drilling with the casings because of the smaller pipe diameter,” said Gustafson.

Trenchless purchased the 15 in. pipe auger and casings for the project and rented the larger auger and casings for the 24 in. pipe from ICON.

“ICON was instrumental in securing the tooling and special equipment required for the specific pipe sizes on the project,” continued Gustafson. “ICON’s personnel were always available for consultation and visited the project during construction to assure us that we were using the recommended procedures.”

Trenchless was able to complete this first-of-a-kind project for Washington State within the allotted time and avoided equipment malfunction delays.

“ICON is a very customer focused, professional and knowledgeable company,” said Gustafson. “Their support and service is top notch. I look forward to a continued relationship with ICON in the future.”

For more information on Trenchless Construction Services, call 360/474-0123.

For more information on ICON, call 800/836-5011 or visit www.iconjds.com.




Today's top stories

Blalock Crews Build TDOT's $67M Newport Bypass

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Equip Expo's Summer Giveaway Offers a Chance for Lifetime Trade Show Registration, Gift Card, Hotel Stay

Tennessee's Pugmill Systems LLC Expands Its Product Offerings to Include Concrete Plants

ASCENDUM Machinery Opens New Savannah, Ga., Facility


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA