List Your Equipment  /  Dealer Login

USACE Awards $1.068B of New Soo Lock Phase 3 Contract

Wed July 20, 2022 - Midwest Edition #15
U.S. Army Corps of Engineers, Detroit District


The New Lock at the Soo Artistic Rendering depicts how the Soo Locks will look once the New Lock at the Soo is complete in Sault Ste. Marie, Mich.
The New Lock at the Soo Artistic Rendering depicts how the Soo Locks will look once the New Lock at the Soo is complete in Sault Ste. Marie, Mich.

U.S. Army Corps of Engineers (USACE), Detroit District anticipates Phase 3 construction will start this summer with the $1.068 billion of the New Lock at the Soo Phase 3 contract award July 1, 2022.

Kokosing Alberici Traylor LLC (KAT), a joint venture headquartered in Westerville, Ohio, will begin constructing the largest phase, the new lock chamber and rehabilitation of the downstream approach walls. This contract allows the contractor to begin work. With continued funding, the remaining work, valued at $803.95 million, may be awarded over the next three years. Corps of Engineers officials expect Phase 3 construction to take seven years.

"The Corps of Engineers looks forward to beginning construction on the new lock chamber later this summer, and we continue to work hard to maintain the pace and continue to make progress toward New Lock at the Soo total project completion in summer 2030," said Mollie Mahoney, New Lock at the Soo project manager.

With Phase 1 nearly complete and Phase 2 scheduled for completion in summer 2024, the third construction phase is a big milestone for the project. A major cost increase led to a five-month contract award delay while the Corps of Engineers developed necessary reports to deliver a new cost estimate for reauthorization to Congress. The cost increase root causes are changing market conditions, inflation, a nationwide labor shortage, design modifications and early estimate assumptions.

The changes in cost since the project's authorization in America's Water Infrastructure Act of 2018 are: first cost changed from $922 million to $2.932 billion, and the project fully funded cost changed from $1.031 billion to $3.189 billion. The project first cost is for project authorization use and calculated in today's dollars. The project fully funded cost allows for escalation through the construction mid-point and anticipates what the project will cost.

The project's first phase to deepen the upstream channel began in spring of 2020 and is substantially complete with punch-list items and final cleanup remaining. The project's second phase to rehabilitate the upstream approach walls began in spring of 2021 and is scheduled to be complete summer of 2024.

The Soo Locks are situated on the St. Marys River at Sault Ste. Marie, Mich., and allow vessels to transit the 21-ft. elevation change at the St. Marys Falls Canal. More than 88 percent of commodity tonnage through the Soo Locks is restricted by vessel size to the Poe Lock. This new lock project will construct a second Poe-sized lock (110 ft. by 1,200 ft.) on the existing decommissioned Davis and Sabin locks site.

A 2015 Department of Homeland Security study estimates a six-month Poe Lock closure would temporarily reduce the U.S. gross domestic product (GDP) by $1.1 trillion, resulting in the loss of 11 million jobs. This Great Lakes Navigation System critical node is essential to U.S. manufacturing and National Security according to the study.

For more information, visit lre.usace.army.mil/About/Highlighted-Projects/New_Soo_Lock/.




Today's top stories

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

Larry Young Paving Tackles Grade-Separated Interchange in Texas

Caltrans, Crews Working to Repair Highway Landslides

FIRSTGREEN Industries Launches ROCKEAT Electric Skid Steer Loader

'Tiltrotator Effect' Increases as Energy Consumption Goes Down

VIDEO: Birmingham, Ala., Awarded $14.5M Fed Grant to Revitalize Its 'Black Main Street'

Pettibone Celebrates 75th Anniversary of Cary-Lift

Fay Preps Way for Pittsburgh International Airport Modernization Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA