List Your Equipment  /  Dealer Login

Wagman Leads MD 32 Widening Work

Thu December 30, 2021 - Northeast Edition #1
Brenda Ruggiero – CEG Correspondent


Construction started in June 2019 on the $126.8 million project, which was awarded to Wagman Heavy Civil Inc. of York, Pa.
Construction started in June 2019 on the $126.8 million project, which was awarded to Wagman Heavy Civil Inc. of York, Pa.
Construction started in June 2019 on the $126.8 million project, which was awarded to Wagman Heavy Civil Inc. of York, Pa. A Maryland Department of Transportation State Highway Administration (MDOT SHA) project involving MD 32 at Linden Church Road in Howard County is heading toward a summer 2022 completion date. The contract calls for the installation of two 12-ft. lanes in each direction, along with 4-ft. inside and 10-ft. outside shoulders in each direction and a 34-ft. open section median. The 6.6-mi. project involves widening a section of MD 32 (Patuxent Freeway) from a two-lane road to a four-lane highway. Seen here is the new Triadelphia Road Bridge. Shown here are the old and new culverts.

A Maryland Department of Transportation State Highway Administration (MDOT SHA) project involving MD 32 at Linden Church Road in Howard County is heading toward a summer 2022 completion date.

Construction started in June 2019 on the $126.8 million project, which was awarded to Wagman Heavy Civil Inc. of York, Pa.

The 6.6-mi. project involves widening a section of MD 32 (Patuxent Freeway) from a two-lane road to a four-lane highway.

The contract calls for the installation of two 12-ft. lanes in each direction, along with 4-ft. inside and 10-ft. outside shoulders in each direction and a 34-ft. open section median. In addition, a new two-lane access road will be constructed west of MD 32 from Vistaview Drive to MD 144 and the Triadelphia Road Bridge over MD 32 was reconstructed, completed in September 2020.

Additional work includes proposed storm water ponds and swales to remove pollutants from storm water runoff, new drainage culverts and box culverts, landscaping and reforestation, new signage, lighting and signals and a variety of drainage, precast box culverts and bridges with caisson foundations and pile foundations.

"There are several streams and waterways within the project limits, so environmental regulations must be considered at every step," said Shantee Felix, assistant media relations manager of MDOT SHA. "Two new bridges are being constructed over the Middle Patuxent River and Terrapin Branch waterways. The project limits include many communities [some homeowner associations], businesses, an MDOT SHA maintenance shop and a school. With all those entities, there are many voices to listen to and take into account, especially when closing a roadway or doing overnight work."

Felix said that this is Phase II of the MD 32 Widening project. Phase I was completed just prior to this project and many of the same people, including contractors and their staffs, who worked on Phase I also are working on Phase II.

"This phase is using the ‘Design-Build' process," Felix said. "The Design-Build process is a project delivery method where the design and construction are performed by a Design-Build team [a contractor and an engineer] that must meet design requirements set forth by MDOT SHA and other regulatory agencies. The Design-Build process can shorten the overall duration of a project, reduce costs and foster innovation in design and construction. So, design is fluid and being completed the same time as construction, instead of months or years in advance."

She added that this project is needed to reduce congestion and increase safety along MD 32.

"This is a heavily traveled roadway that sees between 24,000 and 40,000 vehicles on average every day depending on the section," Felix said. "It is also a popular commuter route."

Major subcontractors for the project include CJ Miller for asphalt paving, Machado for concrete, Guardrails Etc. for guardrail, Traffic Systems Inc. for electrical, Ortiz Trucking for hauling, RLO for site clearing, Ed's Plant World for landscaping, site services, erosion and sediment and seeding and Zone Striping for pavement markings.

Felix reported that a total of 75 to 100 people are working on the project, including design, construction and management.

The project includes 50,000 linear ft. of W-Beam guardrail, 500,000 cu. yds. of earthmoving excavation and grading, more than 5,000 cu. yds. of cast in place concrete, and approximately 100,000 tons of hot mix asphalt paving.

Major equipment includes a Terex HC110 crane, a Link-Belt LS-218H II crawler crane, a Kobelco CK1100G hydraulic crawler crane, an American 9299 lattice-boom crawler crane, a Terex RT335 rough-terrain crane, a Grove RT760E rough-terrain crane, a Grove RT 880E rough-terrain crane, a Sterling/Terex 7501/4792 boom truck crane, a Caterpillar TH63 telehandler, several JLG telescopic boom lifts, a Komatsu PC88MR-10 compact excavator, a Case CX 210 excavator, a Caterpillar 315DL hydraulic excavator, a Caterpillar 320CL hydraulic excavator, a Komatsu PS238-USLC-11 tail-swing excavator, a John Deere 350GLC mid-size excavator, a Komatsu PC360LC-10 crawler excavator, a Komatsu PC360LC-11 hydraulic excavator, a John Deere 470G large excavator, a John Deere 220D mobile excavator, a John Deere 230GW wheeled excavator, a Caterpillar 416C IT backhoe, a Komatsu D65EX-12 crawler dozer, a John Deere 450K-LGP crawler tractor and several Cat crawler tractors.

Other equipment includes a group plant, drilling rigs, a Soilmec SR-75 piling rig, several air compressors and welder generators, light towers, a Bidwell 2450 paver, message signs, hydraulic breakers, a Bobcat/Melroe 72-in. sweeper, a Rome TACW16 tractor and a Finn T 75 T hydroseeder. CEG




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA