List Your Equipment  /  Dealer Login

$2B Light Rail Expansion Benefits Twin Cities

Wed September 04, 2019 - Midwest Edition #18
Eric Olson –CEG Correspondent


Southwest Station in Eden Prairie, on the southern end of the Green Line Extension. The station has only recently opened for bus service, with the rail line to come at a later date.
Southwest Station in Eden Prairie, on the southern end of the Green Line Extension. The station has only recently opened for bus service, with the rail line to come at a later date.
Southwest Station in Eden Prairie, on the southern end of the Green Line Extension. The station has only recently opened for bus service, with the rail line to come at a later date.
 A look at the track work being conducted at the Golden Triangle Station in Eden Prairie.
 Due to vibration-sensitive businesses with daytime operations in the area of Golden Triangle Station, night piling will begin in early September and will last several months as crews complete the work.
 At the Excelsior Blvd. area in Hopkins, crews removed trail pavement and began excavation for the LRT bridge piers over the thoroughfare. The demo of the old Cedar Lake Regional Trail over Louisiana Avenue in St. Louis Park happened in July-August. It will be replaced by a new bridge that will accommodate the trail and the LRT.
 Linden Yards, a city-run recycling and scrap-metal yard just west of downtown Minneapolis, is being used to reprocess old materials demoed from the route of the new LRT.
 The Glenwood Avenue bridge in downtown Minneapolis is being demolished, with a new replacement structure to be built in the next two years. Here, it crosses Cedar Lake Trail and the freight rail, which will be re-purposed for the SWLRT.

Despite not being ready until 2023, the people of the Minneapolis-St. Paul metro area have something worth looking forward to.

That's when the newest light-rail line in Minnesota will be completed, designed to give riders in the southwest suburbs an easier, quicker and alternative way to reach the Twin Cities. Though the rail line may be light, it's safe to say the project is simply massive.

Last November saw the groundbreaking for the 14.5-mile-long Metro Green Line Extension, better known as the Southwest LRT, but the first real heavy construction began in May after the Minnesota winter passed. The light rail service will run between Minneapolis and head southwest toward the towns of St. Louis Park, Hopkins, Minnetonka, Edina and Eden Prairie.

The project has an estimated price tag, when finished, of $2 billion — funded by a combination of federal, county, state and local resources. Included in the contract is the building of 16 new stations along the route, along with 29 new bridges, the modification of seven existing bridges, the construction of six pedestrian tunnels, two cut-and-cover LRT tunnels, 117 retaining walls and the placement of 153,000 feet of track. Officials expect the effort will create 7,500 construction jobs.

The SWLRT alignment will be installed through eight miles of a freight-rail corridor and 6.5 miles of greenfield land, which includes wetlands, undulating topography and roadways.

The scale and cost of the project makes it the largest in Minnesota history, according to the Metropolitan Council, the regional governmental agency in charge of the entire Twin City public transportation system.

Connecting Suburban to Urban

The council is confident the ambitious benefits of the Green Line Extension will match the costs of building it.

"SWLRT will be a major transportation artery that will connect people to jobs, allow upward economic mobility, attract new development and residential opportunities, and create a one seat ride from the southwest suburbs to the many attractions in Minneapolis and St. Paul," said Trevor Roy, senior communications specialist with Metro Transit, a department within the council.

Planners and designers are also betting the SWLRT, in combination with the area's other public transportation services, will help alleviate the often-crippling traffic congestion on the Metro area's roads and freeways.

A small amount of the light rail service runs adjacent to the area's existing highways and roadways, but Roy added that one of the benefits of a shared-use rail corridor is the minimal impact on roads as an existing freight rail is already in operation. The alignment is not located in a traditional urban area, which also minimizes traffic impacts, he said.

Designed to Keep People Moving

The fast and quiet Metro transportation service is part of an integrated system of transitways, including connections to the METRO Blue Line, the Northstar Commuter Rail line and many bus routes.

Both the Blue Line and the current Green Line each saw their highest annual ridership ever in 2018. Nearly 13.8 million rides were transported on the Green Line last year alone, with more than 42,500 rides on average each weekday. The Metro Council projects 34,000 daily riders on the Southwest LRT when it is fully operational.

In anticipation of that, Roy said 27 sleek, light rail vehicles (LRVs) are currently being built by Siemens for the SWLRT. They will operate via overhead electrified lines and run on standard gauge tracks.

The first SWLRT station in Minneapolis is located adjacent to Target Field, home of baseball's Minnesota Twins. The stop has served as a hub for other light rail and bus routes, and from there SWLRT riders will be able to continue along the established 11-mile-long Green Line east across the Mississippi River to the University of Minnesota campus and onto downtown St. Paul.

The new Green Line extension can also intersect with the Metro Blue Line at Target Field. That rail service can take them to a Minnesota Vikings game at US Bank Stadium or to other southern points such as the airport, before ending at the Mall of America station in Bloomington.

Crews Busy Up and Down the Line

The Metro Council is overseeing all of the work on the Green Line extension and have contracted with the Lunda/McCrossan Joint Venture, located in Black River Falls, Wis., and Maple Grove, Minn., respectively, for the civil construction portion of the project. Roy said a separate systems contract will be awarded later for the installation of electrical systems, communications equipment, lighting and overhead catenary lines.

In the meantime, construction is hopping across the entire alignment, including all bridge and tunnel work, Roy reported.

As the Southwest LRT will operate in a shared use corridor with freight rail, light-rail track will be constructed adjacent to existing freight rail. Therefore, one of the first jobs for the contractors was to build new tracks for the freight trains so they can continue operating in the shared corridor while the light tracks are being installed.

At another point on the SWLRT south end in Eden Prairie, the new Southwest Station recently opened as a bus park-and-ride facility until the light rail line is built and connected to it.

The following is a sampling of the multi-stage work zones along the Southwest LRT route that have seen increased activity in the last few weeks:

  • In late August, heavy equipment was hard at work building a Southwest LRT bridge at I-494 and Flying Cloud Drive in Eden Prairie. A crane was stationed in the median of the freeway and the installation of sheet piling for the bridge pier construction had begun. As a result, the I-494 eastbound ramp to Trunk Highway (TH) 212 was closed Aug. 12 for at least seven weeks.
  • Nearby at the new Golden Triangle Station, crews are busy driving pile, often six days a week. Night-time piling work is underway between the hours of 1-7 a.m., a task that Roy said may continue for several months. Efforts have been made, though, to reduce the noise generated by equipment. Over 100 piles have been driven in the area already, but it will become an on-going activity between Golden Triangle north to Shady Oak Road until sometime next summer.
  • At the Excelsior Boulevard area in Hopkins, a temporary parking lot on the west side of the Hopkins Depot is complete and open to the public. Crews are excavating for the piers that will support the SWLRT bridge over the boulevard, and work should intensify in the coming weeks. The removal of existing freight track is also underway. A full closure of Excelsior at the railroad crossing is expected for approximately one month, with an additional closure needed later in the fall to complete this phase of the work.
  • In St. Louis Park, along TH 100, the builders are re-positioning the existing freight rail bridge and erecting a new LRT bridge over the state roadway. Center-pier bridge work began the week of Aug. 12 and vehicle traffic was shifted to create a workspace in the median. The work also caused some nightly lane closures on TH 100.
  • Glenwood Avenue in downtown Minneapolis, near Target Field, was closed in July for the next two years between Lyndale Avenue and 11th Street. The closure is needed for the reconstruction of the Glenwood Avenue Bridge over the Cedar Lake Regional Trail as part of the Southwest LRT project. The Metro Council wants to improve pedestrian and bicycle connectivity through the corridor to help generate transit ridership at the new Royalston Station, the last stop before Target Field. Crews recently removed the bridge deck and are beginning the removal of the bridge girders and substructure.

Another big part of the project involves dealing with areas of unstable soils and soil contamination along the Green Line Extension, with compressible soils chiefly found in the western portion of the alignment. The route includes cut-and-cover LRT tunnels under Trunk Hwy. 62 in Eden Prairie and in the Kenilworth Corridor area of Minneapolis.

Roy said contractors will remove and properly dispose of nearly 150,000 tons of contaminated soil from the corridor, as approved by the Minnesota Pollution Control Agency. Sources of contamination include petroleum from gas stations and former diesel locomotive fueling, solvents from industries and shops and lead, hydrocarbons and other materials from former industrial activities.

"The project will also re-use about 400,000 cu. yds. of excavated fill that would otherwise be destined for a landfill," Roy continued. "Soil removed from one part of the project and re-used in another location reduces the carbon footprint because of less trucking and the use of less landfill space."

A Solid Project Team

Overall, Roy said the Green Line Extension project has been largely problem-free in its first few months of construction. With a veteran construction team steering the work, he doesn't anticipate any issues that will significantly push the completion past 2023.

"With a project of this scope there are always challenges to overcome," he explained. "However, we feel confident that they can be solved thanks to our strong relationships with our project partners and our stellar team at the project office." CEG




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA