List Your Equipment  /  Dealer Login

Bridge Deck Preservation Nears Completion

Atlas Copco’s Dynapac F800T tracked paver joins the company’s 10-ft. (3 m) highway class paver range.

Wed September 09, 2015 - Northeast Edition
Brenda Ruggiero


WVDOT  photo. 
The West Virginia Division of Highways is nearing completion of a project to rehabilitate a total of 19 bridges along Interstate 64 in the Charleston area.
WVDOT photo. The West Virginia Division of Highways is nearing completion of a project to rehabilitate a total of 19 bridges along Interstate 64 in the Charleston area.
WVDOT  photo. 
The West Virginia Division of Highways is nearing completion of a project to rehabilitate a total of 19 bridges along Interstate 64 in the Charleston area. WVDOT photo. The project began on April 4, 2015, and the original completion date was set for Oct. 28, 2015. However, it was extended due to weather and project issues, and estimates now have the project completed before the Thanksgiving holiday.
 WVDOT photo.
The $18 million contract was awarded to Kokosing Construction Company Inc.
 WVDOT photo. The contract calls for the rehabilitation of 19 bridges along Interstate 64, beginning at the Eugene Carter Memorial Bridge (also known as Fort Hill Bridge) and ending where the Brooks Street on-ramp enters the interstate. WVDOT photo. Numerous expansion joints will be replaced, repairs will be made to barriers, a latex modified concrete overlay will be applied to bridge decks, and several cathodic protection systems will be replaced. WVDOT photo. To install the contra flow lane and safety barrier for the construction crews, Kokosing used a 20-ton (18.14 t) rubber-tired excavator with a bracket attachment to move nearly 20,000 ft. (6,096 m) of temporary barrier wall.

The West Virginia Division of Highways is nearing completion of a project to rehabilitate a total of 19 bridges along Interstate 64 in the Charleston area.

The project began on April 4, 2015, and the original completion date was set for Oct. 28, 2015. However, it was extended due to weather and project issues.

The $18 million contract was awarded to Kokosing Construction Company Inc., where Mike Koelbl is the vice president. Jason Jackson serves as the field engineer on the project.

The contract calls for the rehabilitation of 19 bridges along Interstate 64, beginning at the Eugene Carter Memorial Bridge (also known as Fort Hill Bridge) and ending where the Brooks Street on-ramp enters the interstate. Numerous expansion joints will be replaced, repairs will be made to barriers, a latex modified concrete overlay will be applied to bridge decks, and several cathodic protection systems will be replaced. Four structures utilize the cathodic system, which is a technique used to control corrosion of metal in the bridge deck.

“Kokosing Construction is the first contractor in West Virginia to implement a traffic control pattern known as contra-flow,” said Scott P. Love, PE, of Kokosing’s highway division. “The contra flow lane allows the public and highway construction workers to travel safely and work efficiently within the I-64 construction zone. Kokosing Construction also is installing a new cathodic protection system, a complex rehabilitation method that electrifies a titanium layer within the concrete to protect against corrosion to help sustain a concrete structure’s integrity.”

To install the contra flow lane and safety barrier for the construction crews, Kokosing used a 20-ton (18.14 t) rubber-tired excavator with a bracket attachment to move nearly 20,000 ft. (6,096 m) of temporary barrier wall. To remove and install the 86 expansion joints on the interstate system around Charleston, Kokosing used a 43 ft. (13.11 m) boom operated forklift, known as a telehandler, paired with the versatile construction 107 hp backhoe.

To replace the bridge deck surface, a Kokosing subcontractor, the Velotta Company, used a flexible concrete paver to pave more than 3,000 sq. yds. (2,294 sq m) — half a football field — of smooth concrete in one night.

Velotta is overlaying the new concrete deck, paving more than 31,000 sq. yds. (23,701 sq m) of smooth concrete for the I-64 traveling public. Modified Concrete is providing the nearly 2,000 cu. yds. (1,529 cu m) of latex modified concrete used to overlay the concrete deck. Mid-Atlantic Maintenance is providing the numerous traffic control signs and devices to keep the traveling public aware and safe when traveling through the construction zone.

Pullman was subcontracted to rehabilitate and metalize the undersides of the Eugene Carter Bridge. Metalizing provides the Al-Zn-In protective surface that absorbs the corrosive chemicals that deteriorate a structure.

Essroc Concrete is providing more than 600 cu. yds. (458.73 cu m) of concrete to Kokosing Construction for the replacement of the 86 expansion joints and 1,200 ft. (365.76 m) of barrier wall.

Michael Baker International is the designer and inspector of the design-build project.

“Ongoing efforts for effective communication, a hard-at-work attitude, and determination to provide the best product for the owner and their contractors is leading this project to be a success for all,” Love said.


Today's top stories

North Causeway Bridge Offers Innovation, Congestion Relief for Fort Pierce, Fla., Motorists

Missouri's $284M Chester Bridge Under Construction

Mecalac Offers Telescopic Wheel Loader to Improve Stability, Mobility in Material Handling Applications

Chicago Bears Announce Plans for New Enclosed Stadium

Oshkosh Corporation to Acquire AUSA

Webuild Ready to Rebuild Collapsed Baltimore Bridge

Crews Complete Covington, Georgia Community Project

Alabama AGC Announces BUILDSouth Award Winners


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA