List Your Equipment  /  Dealer Login

Effort to Repair Seattle Tunnel

The job to repair the giant tunneling machine stuck under downtown Seattle is going more slowly than expected.

Thu August 07, 2014 - West Edition
Construction Equipment Guide


SEATTLE (AP) An effort to repair the giant tunneling machine stuck under downtown Seattle is going more slowly than expected.

The state Transportation Department said July 28 it had been informed by the contractor, Seattle Tunnel Partners, that it’s taking longer than expected to construct an underground shaft that will allow crews to reach the machine’s damaged cutter head.

The DOT said it’s "no easy task" to build a concrete ring that’s 80 ft. (24 m) wide and 120 ft. (36.5 m) deep. Work on the shaft was expected to be done in July, but could take until the end of August. After the pit is finished, crews will use a massive crane to lift the head of the machine to the surface to repair seals and bearings.

The contractor still expects to resume digging next March and hopes to have the tunnel open in November 2016.




Today's top stories

North Causeway Bridge Offers Innovation, Congestion Relief for Fort Pierce, Fla., Motorists

Missouri's $284M Chester Bridge Under Construction

Mecalac Offers Telescopic Wheel Loader to Improve Stability, Mobility in Material Handling Applications

Chicago Bears Announce Plans for New Enclosed Stadium

Oshkosh Corporation to Acquire AUSA

Webuild Ready to Rebuild Collapsed Baltimore Bridge

Crews Complete Covington, Georgia Community Project

Alabama AGC Announces BUILDSouth Award Winners








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA