Effort to Repair Seattle Tunnel

The job to repair the giant tunneling machine stuck under downtown Seattle is going more slowly than expected.

Thu August 07, 2014 - West Edition
Construction Equipment Guide


SEATTLE (AP) An effort to repair the giant tunneling machine stuck under downtown Seattle is going more slowly than expected.

The state Transportation Department said July 28 it had been informed by the contractor, Seattle Tunnel Partners, that it’s taking longer than expected to construct an underground shaft that will allow crews to reach the machine’s damaged cutter head.

The DOT said it’s "no easy task" to build a concrete ring that’s 80 ft. (24 m) wide and 120 ft. (36.5 m) deep. Work on the shaft was expected to be done in July, but could take until the end of August. After the pit is finished, crews will use a massive crane to lift the head of the machine to the surface to repair seals and bearings.

The contractor still expects to resume digging next March and hopes to have the tunnel open in November 2016.




Today's top stories

Filling the Labor Pool — Post-Pandemic, Construction Industry Wants Workers to Jump in

Farmington Bay Constructors Begin 750M Project

OSHA COVID Safety Rules Give Workplace Flexibility to Transportation Construction Firms

HIgh Reach Excavators Raze Former Jail Site

Case to Host Live Virtual Event Detailing Technology, Options, Advantages of Excavators Outfitted With Machine Control

Pettibone Adds T1056X Telehandler to Traverse Lineup

Reed & Reed Leads Twin Bridges in Vermont to Mid-Summer Completion

GUCA Announces New Board Members, Award Recipients








ceg-logo ceg-logo ceg-logo ceg-logo ceg-logo