Hot Construction Market Puts Pharmacy School Over Budget

Bids were between $2.5 million and $5.5 million higher than expected, which industry experts say is due to one state's hottest-ever construction market.

Tue February 16, 2016 - West Edition
Construction Equipment Guide


University of Hawaii spokesman Dan Meisenzahl says a few options are being considered, but he declined to mention specific courses of action for the pharmacy school project.
University of Hawaii spokesman Dan Meisenzahl says a few options are being considered, but he declined to mention specific courses of action for the pharmacy school project.

HILO, Hawaii (AP) - Bids to build the University of Hawaii's new pharmacy school in Hilo are at least $2.5 million more than expected.

The university budgeted $30 million for the pharmacy school's construction. Bids were between $2.5 million and $5.5 million higher, which one industry expert says is due to Hawaii's hottest-ever construction market, Hawaii News Now reported (http://bit.ly/20UkwEb ).

“This is the hottest construction market that has ever existed in the state of Hawaii,” said John White, the executive director of the Pacific Resource Partnership representing the Hawaii Carpenters union as well as 240 contractors. “Last year, there was about $5 billion of construction projects permitted alone. That was about a 23 percent increase over the previous year.”

White said it's harder and more expensive to find workers.

University of Hawaii spokesman Dan Meisenzahl says a few options are being considered, but he declined to mention specific courses of action for the pharmacy school project.

He said generally, projects that come in over budget can be scaled back to lower the price tag, put out for bid again, or money can be found to increase the budget.

Meisenzahl says the pharmacy project's over-budget bids have caused a two-month delay that could grow.

UH project documents show bids higher than expected in other projects. Bids for air conditioning replacements were generally between $100,000 and more than $300,000 over budget.

Meisenzahl says the university plans to have one company design and build large projects in the future rather than using separate firms for design and construction.

“That's the thing that we've identified as being a more efficient way to get these projects completed on budget and on time,” he said. “And that's obviously our very important goal.”




Today's top stories

Missouri's $284M Chester Bridge Under Construction

Reconstruction of Frank J. Wood Bridge in Maine Under Way

Mecalac Offers Telescopic Wheel Loader to Improve Stability, Mobility in Material Handling Applications

Oshkosh Corporation to Acquire AUSA

Buffalo Looks to Improve, Protect Ralph Wilson Park

Webuild Ready to Rebuild Collapsed Baltimore Bridge

Officials Break Ground On $300M Terminal 3 at O'Hare International

Chicago Bears Announce Plans for New Enclosed Stadium


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA