List Your Equipment  /  Dealer Login

Lake Mead Drinking Water Project Meets Big Milestone

Wed January 02, 2019 - West Edition #1
Henry Brean – LAS Vegas Review-Journal


Construction crews at Lake Mead are ready to let the water win.
(Southern Nevada Water Authority photo)
Construction crews at Lake Mead are ready to let the water win. (Southern Nevada Water Authority photo)

LAS VEGAS (AP) After a three-year battle to keep their underground job site from flooding, a construction crew at Lake Mead is ready to let the water win.

Workers will shut off pumps keeping the water out and allow it to fill a cavern they have carefully excavated from the rock more than 500 ft. beneath the shore.

The move will mark the latest milestone for the Southern Nevada Water Authority's low-lake-level pumping station, a $650 million safety net for a region of 2.2 million residents and more than 40 million tourists that draws 90 percent of its drinking water from the Colorado River reservoir behind Hoover Dam.

The pumping station, on track for completion in early 2020, will let Las Vegas keep drawing water even if the drought-stricken lake shrinks another 200 ft. to "dead pool," the point at which Hoover Dam can no longer release water downstream.

"This project is drought-driven," Erika Moonin, project manager for the Las Vegas-based authority, told the Las Vegas Review-Journal during a recent final media tour of the underground pump station forebay.

Water dripped from the ceiling and spouted from the walls as a small group of reporters and project officials viewed a subterranean waterfall tumbling down from one of the two vertical shafts providing access to the construction zone.

The mix of lake water and groundwater, some of it thermally heated to a comfortable bath temperature, is flooding in from cracks in the surrounding rock.

The forebay is longer than a football field, about the width of three freeway lanes and four stories high, with 34 openings in the ceiling. Each leads 500 ft. to the lake surface.

"I get cell service under shaft 19," Robin Rockey, the authority's liaison to the project, said with a laugh.

Temporary pumps have been removing about 525 gal. of water a minute from the work area. Once those pumps are off, the space should flood within three or four days.

Then a remotely controlled underwater drone will be sent in to unscrew bolts from a massive bulkhead separating the pumping station from the rest of the authority's new plumbing at Lake Mead: a 3-mi., $817 million "straw" that was finished in 2015 and reaches to the bottom of the reservoir.

"There aren't very many projects like this in the world," said Jordan Hoover, project manager for Montana-based Barnard Construction Co., general contractor for the pump station.

The completed facility will be able to draw up to 900 million gal. of water a day from the deepest part of Lake Mead using 32 specially-designed submersible pumps that can produce up to 5,200 hp.

"In combination of depth and flow, they are the largest in the world," Moonin said.

The pumps are manufactured in Spain and shipped to the Port of Long Beach, Calif., where they are loaded onto trucks for delivery to Southern Nevada. It takes four to five truckloads to deliver a single pump. The entire trip from factory to job site takes about a month, Hoover said.

Sixteen pumps have been delivered so far. Moonin said the first should be installed sometime in February.

The construction crew of about 125 people also is hard at work on an electrical and maintenance building, a dedicated, 65-megawatt electrical substation and a pair of 12-ft.-diameter pipes connecting the pumping station to the community's two water treatment plants.

For more information, visit lvrj.com.




Today's top stories

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120

Skanska Awarded Contract to Develop Offshore Wind Port at South Brooklyn Marine Terminal

Blalock Crews Build TDOT's $67M Newport Bypass

Safer Excavator Maintenance With Enerpac Cube Jack Lifting

New Bridges Part of Iowa's $114M Madison Avenue Project

Connecticut's ARPA Funding Has Led to Downtown Revitalizations in Many Towns

Takeuchi Dealer Alta Equipment Company Opens Tallahassee Location

RIDOT Posts RFP for Washington Bridge Demolition Project


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA