List Your Equipment  /  Dealer Login

Nine I-95 Bridges Being Rebuilt or Repaired in Hampden, Maine

Thu November 12, 2020 - Northeast Edition
MaineDOT


In 2020, temporary diversion roadways and bridges have been constructed in the median of I-95 to maintain two travel lanes in each direction throughout much of the project. (MaineDOT photo)
In 2020, temporary diversion roadways and bridges have been constructed in the median of I-95 to maintain two travel lanes in each direction throughout much of the project. (MaineDOT photo)
In 2020, temporary diversion roadways and bridges have been constructed in the median of I-95 to maintain two travel lanes in each direction throughout much of the project. (MaineDOT photo)

An effort to rebuild and rehab a total of nine deteriorating bridges along four miles of Maine's portion of Interstate 95 currently is under way, with a completion set for late 2022.

The Hampden Bridge Bundle Project, valued at $44.7 million, consists of four northbound/southbound bridge pairs at four different sites along Interstate 95 between Exit 174 and Exit 180 in Maine's mid-south near Bangor.

The Maine Department of Transportation (MaineDOT) is rebuilding eight bridges, while rehabilitating another. Three of the bridge pairs cross Souadabscook Stream and one pair carries traffic over Emerson Mill Road and the Central Maine & Quebec Railway. The sole bridge rehabilitation occurs at the Exit 180 off-ramp on Cold Brook Road over I-95.

Cianbro Corporation of Pittsfield is the general contractor on the New England bridge replacement project.

Hampden bridges on I-95 are approximately 60 years old and are approaching the end of their useful lives, according to MaineDOT. The new spans will include non-corrosive materials to reduce future maintenance needs. The bridges over the Souadabscook Stream will be single-span structures to eliminate the need for piers in the water.

When the Hampden Bridge Bundle Project was being planned, it included the demolition and removal of all eight existing bridges and the design and construction of eight full replacement bridges using the design-build method. The Cold Brook Road Exit 180 off-ramp will consist of pier substructure rehabilitation.

In 2020, temporary diversion roadways and bridges have been constructed in the median of I-95 to maintain two travel lanes in each direction throughout much of the project. After the diversions were installed, the northbound traffic on the interstate moved to the median roadway while the northbound bridges were under construction.

Once the new northbound bridges are complete, northbound traffic will move onto the new bridges and southbound traffic will move to the median roadway while construction occurs on the southbound bridges. Following completion of the southbound structures, traffic moving in that direction will begin to travel onto those bridges, and removal of the median roadways and bridges will begin.

Median work started in February and will continue through the end of the year. Most of the northbound bridge work will be completed in 2021, and southbound bridge work will be completed in 2022.

To construct the median roadway and bridges in Hampden, there are times that interstate travel lanes are reduced to one lane either northbound, southbound or both. MaineDOT and the contractor are monitoring traffic daily to best adjust the days and times for the lane closures and prevent delays.

By keeping two lanes operating at all possible times, MaineDOT said traffic impacts have so far been minimal and it expects it to remain so throughout the duration of the project.

Traffic will flow freely on all the new bridges in November 2022.




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA