The third death at a World Cup venue in less than a month prompts an immediate halt to construction work at the Sao Paulo site.

Mon December 23, 2013 - National Edition
Tales Azzoni - ASSOCIATED PRESS


SAO PAULO (AP) Public prosecutors want to halt construction at the World Cup stadium where a man fell 115 ft. (35 m) to his death while working on a roofing structure in the jungle city of Manaus.

Prosecutors want the “immediate’’ interruption of work in all areas where laborers need to be high above the ground. They said work should only restart after constructors show that all safety measures are in place at the Arena da Amazonia, the stadium hosting four World Cup matches next June, including England vs. Italy and United States vs. Portugal.

It isn’t clear when the request will be considered by a labor judge.

Work at the venue was interrupted after the Dec. 14 death but was expected to resume on Dec. 15. It was the second death at Manaus’ Arena da Amazonia this year and the third at a World Cup venue in less than a month.

A few hours after the Dec. 14 death, another worker died of a heart attack while paving an area outside the venue in Manaus. Later in the day, a local union threatened to start a strike there to complain about inadequate conditions offered to laborers.

Two workers were killed when a crane collapsed on Nov. 27 as it was hoisting a 500-ton piece of roofing at the Sao Paulo stadium that will host the World Cup opener. Last year, a worker died at the construction site of the stadium in the nation’s capital, Brasilia.

The first death at the Arena da Amazonia happened in March. Another worker died in April at the new Palmeiras stadium, which may be used for teams training in Sao Paulo.

The Arena da Amazonia is among the six World Cup stadiums that will not be delivered by the end of the year as wanted by FIFA because of construction delays.

Prosecutors said workers shouldn’t be allowed back onto the construction site until it’s deemed completely safe.

“There is a need for a detailed report attesting that the minimum safety requirements for laborers working in heights are in place,’’ they said in a statement.

Marcleudo de Melo Ferreira died Dec. 14 while helping to install diamond shaped panels to the latticework of steel girders that form part of the stadium roof. Dozens of laborers were balanced on the girders as they worked. When complete, the panels on the roof are meant to resemble snake scales.

Constructor Andrade Gutierrez said the causes of the accident would be investigated but reiterated its commitment to worker safety.

FIFA and local World Cup organizers expressed condolences for the death and said worker safety was always a priority at all 12 host cities.

Manaus officials want to hold the first test event at the stadium on Jan. 15, with around 10,000 workers who participated in the stadium’s construction serving as spectators.




Today's top stories

Missouri's $284M Chester Bridge Under Construction

Reconstruction of Frank J. Wood Bridge in Maine Under Way

Mecalac Offers Telescopic Wheel Loader to Improve Stability, Mobility in Material Handling Applications

Oshkosh Corporation to Acquire AUSA

Buffalo Looks to Improve, Protect Ralph Wilson Park

Webuild Ready to Rebuild Collapsed Baltimore Bridge

Officials Break Ground On $300M Terminal 3 at O'Hare International

Chicago Bears Announce Plans for New Enclosed Stadium








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA