List Your Equipment  /  Dealer Login

Crews Unearth Artifacts During Excavation for Airpark Project

The ongoing multi-year project to expand the airport by constructing a new runway, taxiway and apron system began in the fall of 2004, and completion is expected by the summer of 2018.

Wed February 22, 2017 - Northeast Edition #4
Brenda Ruggiero


The Delaware Airpark in Chiswold, Del., is in the final stages of an expansion project.
The Delaware Airpark in Chiswold, Del., is in the final stages of an expansion project.
The Delaware Airpark in Chiswold, Del., is in the final stages of an expansion project. Administration (FAA) most recently awarded a grant of approximately $4.6 million to complete the Runway 9-27 project. This final phase involves the conversion of the existing Runway 9-27 to a 35-ft. (10.7 m) wide parallel taxiway), construction of the 35-ft. final connector taxiway to the new 4,200 by 75 ft. (1,280 by 23 m) runway, and associated infrastructure. The ongoing multi-year project to expand the airport by constructing a new runway, taxiway and apron system began in the fall of 2004, and completion is expected by the summer of 2018. The overall project’s purpose is to enhance flight operations and safety. The new system is designed with adequate runway length and apron dimensions to meet current and anticipated future demands of the aviation community Land acquisition, design, environmental, and construction costs associated with this project to enhance the infrastructure at Delaware Airpark will total more than $31 million. To date, a total of 200,000 cu. yds. (152,911 cu m) of earth have reportedly been moved for this phase, and 750 mi. (1,207 km) have been covered with the earthmoving equipment.

The Delaware Airpark in Chiswold, Del., is in the final stages of an expansion project, according to the Delaware River and Bay Authority (DRBA). The Federal Aviation Administration (FAA) most recently awarded a grant of approximately $4.6 million to complete the Runway 9-27 project.

This final phase involves the conversion of the existing Runway 9-27 to a 35-ft. (10.7 m) wide parallel taxiway), construction of the 35-ft. final connector taxiway to the new 4,200 by 75 ft. (1,280 by 23 m) runway, and associated infrastructure.

The ongoing multi-year project to expand the airport by constructing a new runway, taxiway and apron system began in the fall of 2004, and completion is expected by the summer of 2018.

Land acquisition, design, environmental and construction costs associated with this project to enhance the infrastructure at Delaware Airpark will total more than $31 million at the conclusion of this phase. The construction cost is $17,291,686. Funding is 90 percent FAA and 10 percent DRBA. The contract was awarded to George and Lynch and Diamond Materials LLC.

The overall project's purpose is to enhance flight operations and safety. The new system is designed with adequate runway length and apron dimensions to meet current and anticipated future demands of the aviation community.

According to the DRBA, Delaware Airpark serves the general aviation needs of central Delaware and the Capital city of Dover, including the aircraft of the Delaware State University Aviation Program. It is the base for flight training conducted by Delaware State University for the Air Force ROTC program and other clients such as the Department of Interior and NASA.

The project engineer noted that the runway was built on a variety of wetland types. Much of the site was very wet and experiences tidal groundwater. Delaware Department of Transportation (DelDOT) used stone and clean sand where undercut was needed to achieve stable soil, depending on the surface they were building on.

To date, a total of 200,000 cu. yds. (152,911 cu m) of earth have reportedly been moved for this phase, and 750 mi. (1,207 km) have been covered with the earthmoving equipment.

During the course of the excavation project, several artifacts were reported ly found that were typical of various farm houses in the late 18th and early 19th centuries. There also were arrowheads, stone tools and remnants of hearths typical of the area. Historical mitigation was performed by creation of publications detailing the site, and wetland mitigation was performed by the Authority through creation of a wetland at a nearby farm, as well as mitigation sharing with the state at a wildlife preserve.

The 45-acre Delaware Airpark is home to 45 based aircraft and Delaware State University's flight training program, and serves both corporate and recreational flyers year-round. During the summer months, Delaware State conducts NASA and Air Force ROTC pilot training at the facility. —CEG




Today's top stories

Missouri's $284M Chester Bridge Under Construction

Reconstruction of Frank J. Wood Bridge in Maine Under Way

Mecalac Offers Telescopic Wheel Loader to Improve Stability, Mobility in Material Handling Applications

Oshkosh Corporation to Acquire AUSA

Buffalo Looks to Improve, Protect Ralph Wilson Park

Webuild Ready to Rebuild Collapsed Baltimore Bridge

TEC Holds Grand Opening Event in Huntsville, Alabama

VIDEO: Connecticut Officials Celebrate Rapid Reopening of I-95 Bridge After Destructive Fire


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA