List Your Equipment  /  Dealer Login  /  Create Account

Harbor Bridge Project


Harbor Bridge Project Crews Have Productive Summer

The summer months were an incredibly productive time for construction progress around the South Interchange or future tie-in point for IH 37, SH 286 (Crosstown Expressway) and US 181. Despite initial rain delays, roadworks and structure crews met several goals to accomplish major upcoming traffic shifts, connector switches and demolition of existing ramps around the IH 37 and SH 286 Interchange....


CCHB Crew Pours Concrete

Over the past month, crews on the south side of the Harbor Bridge project in Corpus Christi achieved a major milestone with the completion of the largest concrete pour to-date on the project. The pour was part of the construction of the footing for the south pylon and included 3,100 cu....


First Pre-Cast Segment Reaches Corpus Christi Harbor Bridge Work Site

On Sept. 4, the Corpus Christi Harbor Bridge project reached a major milestone when the first pre-cast segment was delivered to its North Approach. The segment weighs 135 tons and is the first of about 2,600....


Harbor Bridge Crews Achieve Project Milestone

Harbor Bridge Project (HBP) crews have reached another milestone with the completion of 40 drilled shafts on both the north and south side of the project. The 40 drilled shafts will make up the foundations of the two bridge pylons....


HBP Crews Provide Recovery Assistance in Wake of Storm

Heavy equipment operators, superintendents, field crew members, subcontractors and employees from all different backgrounds and specialties joined forces to assist with clean-up efforts for those hardest hit by Hurricane Harvey....






ceg-logo ceg-logo ceg-logo ceg-logo ceg-logo
39.04690 \\ -77.49030 \\ Ashburn \\ VA