Construction Crews Complete I-80 Exit Six Months Early

Tue November 03, 2020 - West Edition #23
UDOT


Crews were able to compete the project early because materials for the project became available sooner than expected. The original plan had construction pausing for the winter and finishing in spring 2021, but the contractor on the project was able to speed up work and open the lane six months ahead of schedule.
Crews were able to compete the project early because materials for the project became available sooner than expected. The original plan had construction pausing for the winter and finishing in spring 2021, but the contractor on the project was able to speed up work and open the lane six months ahead of schedule.

A new exit-only lane on westbound I-80 between S.R. 201 and S.R. 36 in Tooele County has opened six months ahead of schedule. This new "auxiliary" lane, designed to provide additional space for entering or exiting the interstate, will improve traffic flow and reduce delays for drivers in the area.

Crews were able to compete the project early because materials for the project became available sooner than expected. The original plan had construction pausing for the winter and finishing in spring 2021, but the contractor on the project was able to speed up work and open the lane six months ahead of schedule.

"Tooele County is growing fast, and this area is a choke point, where a small crash can cause major delays," said Oanh Le-Spradlin, UDOT project manager. "Our goal is to provide a smoother, safer trip for drivers, so we wanted to get this lane opened as quickly as possible."

Despite its relatively short length (about 2 mi.), the project is expected to deliver major benefits for drivers. UDOT traffic engineers calculate that the additional lane will reduce delays by up to five times in incidents where a westbound lane is blocked on the interstate between SR 201 and SR 36.

The project is unique in several ways. Designers and field workers used digital 3-D models for most of the work instead of traditional paper plans, which saved time, improved precision, and reduced waste. In a further effort to improve efficiency and reduce environmental impacts, more than 3,600 cu. yds. of old concrete were crushed up and repurposed to build the new auxiliary lane. And when construction required the closure of the former view area along westbound I-80, the project team partnered with the Daughters of the Utah Pioneers and other organizations to move two historical markers previously located there to a new site near Saltair.

The I-80 westbound auxiliary lane project is one of UDOT's Top 10 projects for 2020 and is one of several improvements recently completed or under construction along I-80 in this area. UDOT continues to work closely with local governments to prioritize and develop projects to meet Tooele County's unique transportation needs.

Construction schedules are weather-dependent and subject to change.

For more information, visit udot.utah.gov.




Today's top stories

Fed Funding to Increase U.S. Battery Production

Teichert Tackles Tough Job Through Teamwork

Maze of Policy Changes May Complicate IIJA Implementation

AECON Installs 50-Ton Girders for New Washington Bridge

VIDEO: Tsurumi Pump Celebrates 100 Years

SPS New England, Select Demo Lead Boston Bridge Project

Alex Lyon Holds Annual Barbecue, Hay Camp, Auction

Kevin Chodkowski Joins Baschmann Services as Sales Representative


 







39.96250 \\ -83.00610 \\ Columbus \\ PA