List Your Equipment  /  Dealer Login

Largest Dam Removal in U.S. History Under Way

Wed May 17, 2023 - West Edition #11
KDRV


The Klamath River Renewal Corporation (KRRC) is leading the historic dam removal project. Kiewit is serving as the prime contractor on the record-breaking construction project.
(KRRC photo)
The Klamath River Renewal Corporation (KRRC) is leading the historic dam removal project. Kiewit is serving as the prime contractor on the record-breaking construction project. (KRRC photo)
The Klamath River Renewal Corporation (KRRC) is leading the historic dam removal project. Kiewit is serving as the prime contractor on the record-breaking construction project.
(KRRC photo) The pre-removal include demolishing 100,000 cu. yds. of concrete, 1.3 million cu. yds. of excavation, 70,000 cu. yds. of “drill and shoot” and 2,000 tons of steel demolition. 
(KRRC photo) The four dams have a combined height of 411 ft. Copco 2, which became operational in 1925, is the shortest of the four with a hydraulic height of 27 ft. and structural height of 63 ft.
(KRRC photo) Crews have begun constructing access roads to allow access for heavy equipment required for further construction activities. Existing bridges will need to be reinforced and new bridges will need to be constructed to enable construction equipment access. (KRRC photo) In total, the four dams impound approximately 15 million cu. yds. of sediment.
(KRRC photo) (KRRC photo)

Construction to start the removal process of the Klamath River dams has begun and all four dams are scheduled to be removed from the river by the end of 2024, according to the latest report from KDRV.

Crews have begun constructing access roads to allow access for heavy equipment required for further construction activities. Existing bridges will need to be reinforced and new bridges will need to be constructed to enable construction equipment access. The Klamath River Renewal Corporation also is in the process of developing several sites to accommodate the workforce, installing job trailers and office space as well as lodging facilities for the construction crews. This is the beginning of a series of enabling construction projects that will take up the remainder of 2023 as crews prepare for drawdown of the reservoirs in January 2024 and the subsequent removal of the dams.

The Federal Energy Regulatory Commission approved this project — the largest dam removal in American history — in November 2022, a project valued at $450 million.

The Klamath River Renewal Corporation (KRRC) is leading the historic construction project. Omaha, Neb.-based Kiewit is the prime contractor on the job while Knight Piesold, headquartered in South Africa, is the civil prime design partner on the project. KRRC took over ownership of the dams from Pacific Power in July 2021. The project is expected to wrap in 2024.

Construction preparation work already is under way at Copco 2.

"That dam and all the facilities associated with Copco 2 at that location should effectively be out of the river no later than September or early October of this year," said Mark Bransom, CEO of KRRC. "[Current] work includes bridge upgrades, new road construction to access the dam sites more easily, worksite development and more."

According to the construction overview, crews will begin drilling and blasting operations at Copco 2 to remove it completely. That portion of the project is expected to be completed by this fall. A restored river channel will be built through the existing dam footprint.

Reservoirs behind the existing dams will be simultaneously drawn down over the next several months and other projects will be completed before the dams are removed. According to reports, the pre-removal include demolishing 100,000 cu. yds. of concrete, 1.3 million cu. yds. of excavation, 70,000 cu. yds. of "drill and shoot" and 2,000 tons of steel demolition.

After Copco 2, the J.C. Boyle Dam will be the second dam removed, followed by Copco 1 and then Irongate, according to the schedule. Restoration of the reservoirs and tributaries will begin in early 2024. The four dams have a combined height of 411 ft. Copco 2, which became operational in 1925, is the shortest of the four with a hydraulic height of 27 ft. and structural height of 63 ft.

In total, the four dams impound approximately 15 million cu. yds. of sediment.

KRRC said it is working with experts to monitor potential impacts to the river in the coming years after the removal of four dams.

"We want to wait a little while to allow the river to sort of find its course again," Bransom said. "Then we'll come in and add a light touch where it's appropriate to do so with some restoration that we believe will be beneficial, primarily for habitat and passage conditions for migrating fish."

One of the goals of removing the dams is to protect the salmon population. KRRC is hopeful that population will return to the river and thrive once again.

"We're really trying to create conditions that are more favorable than those that exist today to support a more healthy environment for all the communities that rely on the river," Bransom said.




Today's top stories

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

Volvo CE Continues to Perform, Transform During Slower Q1 2024

American Bridge Co. Leads Conn.'s East Haddam Swing Bridge Project

Pettibone Celebrates 75th Anniversary of Cary-Lift

Common Ground Alliance Hosts Conference & Expo in Colorado On Preventing Utility Damages

Going Beyond Diversity: Star Equipment's Rental Advantage

Volvo CE Launches Updated L30, L35 Compact Wheel Loaders


 






aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA