List Your Equipment  /  Dealer Login

Laser Scanning Used to Determine Structure’s Soundness

Fri June 24, 2011 - Southeast Edition
Billy Alan Chaves


Defects in a white concrete surface can’t hide from millions of points collected with a high-definition laser scanner.

Things didn’t appear so cut and dried in September 2010, though, when the New Orleans District Corps of Engineers tried to determine if a stage control structure built near Zachary, La., in East Baton Rouge Parish was constructed according to design tolerances. The construction contractor’s surveyor had collected 12,000 shots on the structure surface with a total station without being able to determine if it was within the strict tolerances required. Something more powerful was needed — and laser scanning turned out to be the answer.

The Amite River and its tributary, the Comite River, are the major causes of catastrophic flooding in the Baton Rouge metro area. In 2001, the U.S. Army Corps of Engineers, the state, the Amite River & Tributaries Study Authority and East Baton Rouge Parish signed an agreement to develop a regional solution called the Comite River Diversion Canal Project. Its purpose is to divert about 50 percent of the flood waters from the Upper Comite River to the Mississippi River.

The project will involve construction of a 12-mi.-long diversion channel from the Comite River to the Mississippi River, a diversion structure at the Comite River, guide levees, the Lilly Bayou stage control structure and several drop structures where the diversion channel intersects with roads, railroad bridges and bayous. The project has become even more important since the area has seen explosive growth due to population displacement from the New Orleans area following Hurricane Katrina. As of 2008, the total estimated cost of the project, which is due for completion in 2016, was $187 million.

The Lilly Bayou Control Structure will dissipate the energy of water flowing between the Comite and the Mississippi from a higher to lower elevation, according to Rick Tillman, structural engineer with the Corps. The energy will dissipate as water flows over a spillway featuring an elevated weir.

The $27.6 million second phase of the project consists of excavation and the construction of the concrete control structure, a stilling basin and an outflow channel. The main surface slab was designed to have a 1 to 5 (1v: 5h) slope, a several-feet-thick substructure of mass concrete and large baffle blocks filling the stilling basin at the bottom constructed of 3,000-psi concrete. A 1-foot-thick, 5,000-psi concrete overlay also was placed on top of the substructure to handle the compressive force and abrasion generated by rushing flood waters.

At no more than 1/8 in. (.3 cm) of deviation for every 10 ft. (3 m) of surface, the elevation tolerance on the structure is uncommonly tight, according to Tillman. “That’s out of the ordinary for the [Corps’] New Orleans District to design; however, it’s not unusual for the purpose of the structure,” he said. “We have flow velocities that exceed 40 feet per second. At those velocities, you can get cavitation and if you have unevenness on the surface, it can tear a hole and tear the structure apart. That’s why you have to have these tight tolerances.”

Tillman said that after the structure was built, though, deviations from the elevation tolerance on the sloped face were plainly visible using a straight edge. Determining the extent to which the structure was out of tolerance promised to be quite a task in itself.

The Difference: Quantity of Points

The Corps’ lead engineering technician, Dwayne Blanchard, having experienced previously successful scanning projects that Dale Stockstill & Associates (DS&A), Carriere, Miss., had completed for the division, recommended that Tillman ask them about scanning the structure.

After obtaining the coordinates for the PK nails that were already in place from the construction company’s project surveyor, the crew checked them with its GPT-3105W reflectorless total station from Topcon Positioning Systems and then started the scan using a Topcon GLS-1000 laser scanner.

The elevation did not adhere to tolerance throughout the structure surface, but the X and Y axes were fairly close to tolerance. So the crew performed the scans from the existing control point, which was in place at the top and bottom of the large structure, knowing that the two scans could be corrected during the cloud registration process.

Tillman noted that scanning provided much richer surface detail than shooting in less time than a total station does.

“You can obtain those results on conventional total stations, but this is much quicker,” he said. “They scanned the entire surface of this flume surface — I think it took them two to four hours — and they had something like seven and a half million points. It took about three days to collect about 12,000 points with the conventional total station.”

After the initial scan was completed at the top of the structure, the data file was downloaded for the engineers to view in the construction trailer while the second scan was being taken. It didn’t take long for Tillman’s question to be answered — the millions of points collected on the surface clearly displayed undulations, ridges, dips and humps in the structure.

DS&A technicians used a PolyWorks routine to “color map” the deviations as related to the design plane. DS&A technicians provided traditional cross sections at specified intervals, but because the surface was so large and the tolerances were so tight, many hundreds of sections would have been required just to view a small portion of the slope. DS&A’s technicians went to work programming. They modified some existing routines in their PolyWorks software to generate an ASCII-type EM file —a format favored by the New Orleans District — that converts the point cloud data to a grid every foot laterally and half a foot longitudinally going down the slope. This programming had to be refined several times to deal with file size and computer processing speed.

After the program was refined, it extracted traditional points (point number, Northing, Easting, elevation and code) from the cloud at the specified intervals and wrote them out to an ASCII file. This file was then converted to the New Orleans District’s EM file format, enabling the data to be loaded into the district’s programs for analysis by its engineers and technicians.

In addition to the EM file, the District Engineers requested a contour map —but not just any contour map.

The Corps engineers requested a CAD drawing that depicted the 1v: 5h slope as horizontal and contours that were related to the design plane. DS&A’s technicians created a process that flattened the data onto the slope while maintaining the original project stationing. This required application of a precise scale factor to the data on the slope, i.e., essentially squeezing the hypotenuse down to the base of the triangle. The contour interval was small — five hundredths of an inch — and directly in proportion to the original design.

Officially Scanning

After the Corps received the data in a manner that was easily understandable to all Corps personnel involved — without the need to learn new software or go to a seminar to learn how to interpret a color map — the Corps made the project official. It issued a task order to survey and scan the structure. Corps policies required that the data be recollected because the previous data provided by the contractor were accepted before the scan was performed. DS&A’s crew returned to the project site and started from scratch, checking the project Permanent Bench Mark (PBM) with their Topcon GPS units, running precise three-wire level loops from the PBM to the PK nails on the top and bottom of the structure with its Topcon AT-G1 AutoLevel.

The crew used its Topcon GPT-3105W Reflectorless Total Station in conjunction with its Topcon DL-500 digital level to obtain data under water and mud covering the stilling basin that could not be pumped out. The total station shot the digital level rod for the horizontal position while the DL-500 obtained a precise elevation for each shot. These additional data obtained under the water were checked, compared and incorporated into the point cloud data.

Again the data reflected the deviations from the design criteria and the deliverables were remade using these new data. As of early spring 2011, a process for correcting the structure’s elevations was being worked out.

Based on this project, Tillman is a believer in the use of scanning technology to determine adherence to specifications on structures of such large scale.

“I see other applications of its use that would be beneficial, such as repeat-type surveys that we have to do periodically for movement or settlement.”

Billy Alan Chavers is the owner of Dale Stockstill & Associates, a provider of surveying, mapping and laser scanning services on the Gulf Coast.




Today's top stories

Larry Young Paving Tackles Grade-Separated Interchange in Texas

NAPA Urges Drivers to 'Watch For Us' During National Work Zone Awareness Week

Caltrans, Crews Working to Repair Highway Landslides

Landscapers, Contractors, Dealers Can 'Test Before They Invest' in Equipment in Equip Expo's 30-Acre Outdoor Demo Yard

John Deere Launches Nationwide Search for First-Ever Chief Tractor Officer

Growing Interest in Construction Careers Among Younger People Means Jobs Filled, Deadlines Met

American Bridge Co. Leads Conn.'s East Haddam Swing Bridge Project

New Rocket Park at Huntsville, Ala.'s Space Program Museum Nearing Completion








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA