List Your Equipment For Free  /  Seller Login

Miss. River Span Job Sees Finish Line Ahead

Fri February 01, 2013 - Midwest Edition
Brenda Ruggiero


A huge project involving the Mississippi River Bridge is headed toward completion next year. While the project owners are the Missouri and Illinois Departments of Transportation, the lead is the Missouri Department of Transportation (MoDOT), under project director Gregory Horn. The project is actually made up of nearly 40 smaller projects.

“This helps us to manage the overall cost of construction and allows us to schedule construction around the main span [the bridge],” said Andrew Gates, customer relations representative of the MoDOT St. Louis District.

The full dollar amount of the overall construction project is reportedly about $700 million. The cost of the main span is $239 million. Construction began in Feb. 2010, and the bridge and associated construction is scheduled to be open to traffic by early 2014.

The main span contractor is a joint venture between Massman of Kansas City, Mo., Traylor Brothers of Evansville, Ind., and Alberici of St. Louis, Mo.

The project includes a cable stayed bridge between St. Clair County, Ill., and St. Louis, Mo., and the realignment and reconstruction of Interstate 70 and numerous local roads on both sides of the state line.

According to Gate, the project includes the following key components: Missouri North I-70 Interchange; a roadway connection between the existing I-70 and the new bridge, with further connections to the local street system at Cass Avenue at St. Louis; an Illinois I-70 connection; a roadway connection between the existing I-55/64/70 Tri-Level Interchange and the main span; an Illinois Tri-Level Interchange; and improvements at the I-55/64/70 Tri-Level Interchange in East St. Louis, which will connect to the I-70 connection leading to the main span.

“Working on a river bridge, especially a river bridge over the Mississippi River, is always challenging,” said Horn.

“Early in the project, we lost several months of construction because the river was flowing at or above flood stage. We couldn’t safely stage our construction equipment for the initial foundation work. Now, less than four years later, we are experiencing exceptionally low water levels. That means that our contractor has to continually adjust their process to complete installing sections of the deck and the superstructure.”

Challenging projects often also have some unique aspects, as well.

“One unique element is building an iconic landmark about a mile away from another St. Louis iconic landmark, the Gateway Arch,” Horn said.

“This meant that as we went through the design process, we had to make sure that the new bridge’s design complemented, and in no way overshadowed, the Arch. Another unique element we had to deal with was the rock strength under the river bed. Our contractor suggested an alternate method of constructing the drilled shaft foundation for the bridge, based on special equipment they had. Our contractor proposed to install a test shaft to prove that their design would meet the strength requirements for our foundation. The test shaft maxed out the test equipment, and set a world record for drilled shaft strength.”

The main span construction includes 12,152,790 lbs. (5,512,413 kg) of reinforcing steel in the entire job. Each tower, including footing and shafts, contains 4,442,530 lbs. (2,015,098 kg) of reinforcing steel. There is a total of 16,367,840 lbs. (7,424,327 kg) of structural steel.

The tower height is 400 ft. (122 m), and each tower contains 7,768 cu. yds. (5,939 cu m) of concrete. In addition, each footing has nearly two million lbs. of reinforcing steel, and required 3,600 cu. yds. (2,753 cu m) of concrete. This required 400 trucks to pour continuously over a day and a half.

With a main span of 1,500 ft. (457 m), the bridge will be the third largest cable stayed bridge in the United States. It will require 600 mi. (966 km) of cables, which is enough to stretch between St. Louis and Kansas City and back.

Currently, large equipment on site for the main span construction includes a Manitowoc 7000 ringer barge mounted crane; two Manitowoc 2250 track cranes, one on a barge and one on land; one Leibherr LR1300 track crane on land; two Manitowoc 4100 track cranes on barges, two grove rubber tire cranes, two FabCo tower cranes (one on each tower), and two tugboats.

Throughout the job, additional Manitowoc cranes were used for short durations. This included a 4100 Ringer, a 3900, a 4,000, and two additional 2250s.

Contractors on associated projects include Millstone Bangert, Fred Weber, Keeley and Sons, Kilian, Baxmeyer, Hanks Excavating and Landscaping, Petroff Trucking Company Inc., Insituform Technologies, Hayden Wrecking, Moniger Excavation, Halverson, and Mason Landscaping.


Brenda Ruggiero

Brenda Ruggiero has written for CEG for over 20 years. She lives near the town of Accident in far western Maryland. Her favorite assignments so far involved interviews with Survivor’s Boston Rob and hot dog eating champion Joey Chestnut. Both were involved in construction at one time.

Brenda holds a BA in Mass Communication with a writing focus from Frostburg State University and minors in Public Relations and Political Science. She works full time as a staff writer for a weekly newspaper, the Garrett County Republican. She enjoys feature writing the most, which gives her the opportunity to talk to people and share their stories.

Brenda and her middle school sweetheart, Reuben, have been married for over 34 years and have three grown children and four cats.


Read more from Brenda Ruggiero here.





Today's top stories

Fed Funding to Increase U.S. Battery Production

Teichert Tackles Tough Job Through Teamwork

Maze of Policy Changes May Complicate IIJA Implementation

AECON Installs 50-Ton Girders for New Washington Bridge

VIDEO: Tsurumi Pump Celebrates 100 Years

SPS New England, Select Demo Lead Boston Bridge Project

Alex Lyon Holds Annual Barbecue, Hay Camp, Auction

Kevin Chodkowski Joins Baschmann Services as Sales Representative









39.96250 \\ -83.00610 \\ Columbus \\ PA