List Your Equipment  /  Dealer Login

Scruggs Co. Working to Top 99 Grind-Free Miles

Fri February 26, 2010 - National Edition
Construction Equipment Guide


The Cook County I-75 widening project is a $126 million project between Adel and Lenox, Ga. It’s part of the state’s Fast Forward Program, a $15.5 billion initiative to expedite transportation projects. Part of that initiative includes widening I-75 from four to six lanes throughout parts of Georgia.

The Scruggs Company of Valdosta, Ga., has its GOMACO paving train at work on the project, and it has been achieving good ridability, which means absolutely no grinding on 99 lane mi. (159 km). And the project isn’t even complete yet. The company still has 27 more lane mi. (43.5 km) to pave and it plans on having zero grinding on that section as well.

“We’re dealing with a seven inches per mile maximum on the one-tenth blanking band,” John Romaine, Concrete Division manager of Scruggs, said. “Our average results are in the 1.5 inch range and that includes all the concrete paving on the project, even the short run, leave-out sections. If you take just our mainline runs, we’re under one inch per mile.”

Scruggs used the Leica stringless guidance system on its PS-2600 placer/spreader and four-track GHP-2800 while paving the last 27 lane mi. (43.5 km). It has used the stringless system on grading and site prep equipment, but this was the company’s first time using it to pave.

“Alignment of the PS-2600 is critical for us,” Romaine said. “This is a continually-reinforced concrete [CRC] project and we have only two inches of clearance from the outer edge of the transverse bar assemblies to the inside of the sideforms. It is critical to maintain alignment horizontally and it worked well.”

The concrete is a Georgia Class 1 mix with a size 57 stone and natural sand. Slump averages between 1.25 to 1.75 in. (3.2 to 4.4 cm). It is mixed at an onsite batch plant and delivered by dump trucks carrying 9 cu. yds. (6.9 cu m) loads.

The new Portland cement concrete pavement is being slipformed by a GOMACO GHP-2800 four-track slipform paver. Each paving pass is 25 ft. (7.6 m) wide, 12 in. (30 cm) thick. A side-mounted bar inserter shoots No. 5 bars, 24 in. (61 cm) long, into the side of the slab at 18 in. (45.7 cm) intervals.

“We like our GHP-2800 four-track,” Romaine said. “It gives us flexibility to tackle different types of projects, gives us a good ride, and allows us to pave more accurately.”

A four-track Commander III is slipforming a 12 ft. (3.7 m) wide add-on lane on the project. It also is equipped to pave stringless.

When Scruggs first started using the stringless system, it went through a series of onsite tests with personnel from GOMACO and Leica. Stringline also was set so a GOMACO Smoothness Indicator (GSI) could run behind the paver and provide real-time ride information during the testing.

“It was important to me to have a GSI as part of the paving train during testing,” Romaine said. “It obviously provided some excellent feedback, instantly, so we could make any necessary adjustments.

“We were able to run the 3D model of the project through the GSI software so we could predetermine the best possible ride we could achieve. We discovered, because of the profile grades of the roadway and other factors, the best we could achieve on the IRI would be around a 40. It’s interesting to be able to determine the best ride number you can possibly achieve, no matter what smoothness index you’re using.”

The optional GSITools software gives contractors the ability to build a profile of the project to view various indexes and also estimated concrete yield before paving begins.

A GOMACO T/C-600 texture/cure machine follows behind the paver applying a 0.375 in. (.9 cm) center-to-center horizontal tine and a white spray cure. Sonic sensors, steering off the side of the slab, guide the texture/cure machine.

“I think the future for the stringless system is bright and we’re looking forward to learning more about the system’s true capabilities,” Romaine said. “We’ve gone Leica from bottom to top. We’re building subgrade, base, and now concrete.”

Scruggs’ work on the I-75 project is scheduled for completion by mid-summer 2010. It will spend this summer paving the northbound side of the project, an additional 27 lane mi. (43.5 km), with its GOMACO paving train.

“GOMACO is the best in the business, as far as I’m concerned,” Romaine said. “We get great service out of all the individuals at GOMACO, from their parts people to their engineers to their salesmen. We also get great performance from their equipment. The ease of setup and change-over for different paving widths saves us a lot of time and money.”




Today's top stories

New Bridges Part of Iowa's $114M Madison Avenue Project

Eagle Bridge Co. Works On Final Leg of U.S. 35 Upgrade

Fay Preps Way for Pittsburgh International Airport Modernization Project

SAKAI Achieves Record Sales, Production

Takeuchi Recognizes Top Dealers at 2024 Dealer Summit

Muddy Water Dredging Christens Marlin Class Dredge

Indiana Officials Mark Start of 2024 Construction Season, Promote Safety

Leica Geosystems Launches its First Machine Smart Antenna — Leica iCON gps 120








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.96250 \\ -83.00610 \\ Columbus \\ PA