Technology Speeds Spaceport America Runway Construction

Wed July 13, 2011 - West Edition
Construction Equipment Guide


Construction of a $27-million runway project for Spaceport America is on track for completion nearly two months ahead of schedule, due to machine control technology from Leica Geosystems.

The Spaceport project, located in a remote area 35 mi. southwest of Truth or Consequences, N.M., will make space tourism a reality. The state of New Mexico and two local counties are putting up $198 million for this unique project.

Construction is being greatly accelerated with the aid of GPS and robotic total station machine control from Leica Geosystems, said David Guerra, superintendent of David Montoya Construction, the project’s contractor.

“We should be finished with the runway by the third week in July — almost two months ahead of our scheduled date of September 16,” he said. “And the Leica Geosystems machine control equipment is the reason we’re going to be early.”

After rapid preparation of the subgrade with the Leica PowerGrade 3D GPS-equipped dozers and motorgraders, a GOMACO 9500 Series fine-grade trimmer equipped with Leica PaveSmart 3D takes over to get the subgrade to ± 1/100th foot.

“Using PaveSmart 3D to control the trimmer alone cuts fine grading time to a third of what it takes with a motorgrader,” said Guerra.

Use of the Leica Geosystems 3D-equipped trimmer also should deliver improvements in concrete yields for the paving phase, compared with traditional techniques, according to the manufacturer.

Montoya is now gearing up for paving the 10,000-ft. (3,048 m) long runway with its Guntert & Zimmerman S850 slipform paver. The paver will make six passes, each 33.3 ft. (10 m) wide, to cover the 200-ft. (61 m) runway width. Using high precision Leica robotic total stations, PaveSmart 3D will regulate steer, grade, draft and crossfall of the slipform paver in real-time.

Leica Geosystems Machine control eliminates the labor costs for detailed surveying for the runway, stakeout of hubs, setting bluetops and set up of traditional stringlines used with slipform paving plus data handling between all machines on site becomes easier throughout the entire project.

For more information, visit www.leica-geosystems.us/machinecontrol.




Today's top stories

Jobseekers Leveraging Career Market for In-Demand Skilled Trades

Value in Remanufacturing Construction Equipment: Reduce Cost, Downtime, Carbon Footprint

Buckley, PennDOT Restore I-95 to Usefulness in Philly

Meta Plans to Build $800M Next-Generation Data Center in Montgomery, Ala.

Demolition Crews Bring Down Largest Span of Baltimore's Collapsed Key Bridge

Flo Engineering Restoring Access to Critical Highway in California

Webber Working to Complete $300M Texas Interchange Project

Bobcat Installs Innovative Stationary Fuel Cells From HyAxiom at Two of Its Facilities








aggregateequipmentguide-logo agriculturalequipmentguide-logo craneequipmentguide-logo forestryequipmentguide-logo truckandtrailerguide-logo
39.04690 \\ -77.49030 \\ Ashburn \\ PA